Double Period Batch Job Setup
Go to Setup > Flow > New Flow > Schedule-Triggered Flow
Start Date = set to TODAY
Start Time = 11:00 PM
Frequency = Daily
Add Element > Action > Add Action > search Invoke Double Period Identification Batch >
Label: Invoke Double Period Batch
API Name: auto populated
Start Date and End Date= toggle
Click Start Date field > click New Resource
Resource Type= Variable
API Name = var_StartDate
Data Type = Date
Default Value = type Flow then choose Current Date
It will look like this {!$Flow.CurrentDate}
Click End Date field > click New Resource >
Resource Type = Formula
API Name = var_EndDate
Data Type = Date
Formula = choose variable :var_StartDate + 1
Check Syntax and click Done
Click Done and Save.
Flow Label = Double Period Batch
Click Save and Activate
How it works
Note:
The Double Period Batch will only work on the same Cohort record with 5-minute start time intervals. If 5 minutes are exceeded, it will not be covered in the batch process.
The Double Period Batch will only work on not more than 2 Periods.
1st session will be tagged as Multisession = 1 , 2nd session will be multisession = 2 and session master will be linked to the 1st session.