Pre-Config PosiEd K-12
Note: The Org should have a PosiEd (Parent) package installed first, before installing the PosiEd K-12 (Child) package.
(For an Org that has an existing PosiEd package)
Reason for this config: The Markbook objects (e.g. Assessment), are already removed from the old PosiEd package and were moved to the PosiEd K-12 child package. Markbook objects are still existing in the old PosiEd package that’s why we need to do the following steps below.
If an old version of the PosiEd package is already installed in the Org, and then you are planning to install the PosiEd K-12, follow the criteria below.
Install the latest PosiEd package
Delete the orphan Markbook objects (Assessment, and other related objects) and Grade Scale
To delete, this must be done in a Classic Mode
After the deletion, install the latest version of PosiEd K-12
(For an Org that doesn’t have a PosiEd package installed)
If you have a clean Org, you can install the latest PosiEd package, and then install the PosiEd K-12 child package.